The Alternative Fuels Infrastructure Facility (AFIF) under the Connecting Europe Facility co-funds charging and alternative fuel supply infrastructure within the Trans-European Transport Network, with a view to decarbonising transport in line with the European Green Deal and the AFIR Regulation.


e-handling – Decarbonisation of Spanish airports by introducing electric vehicles by ground handling operators

Co-funded by the European Union

Project co-funded by the European Union through the Connecting Europe Facility – Alternative Fuels Infrastructure Facility (CEF AFIF), managed by CINEA. Grant agreement No 101137350.

• Project number: 101137350
• Project acronym: 21-ES-TG-e-handling
• Call for applications: CEF-T-2021-AFIFGEN • Topic: CEF-T-2021-AFIFGEN-WORKS-ZE
• Type of action: CEF Infrastructure Projects.
• Granting authority: European Climate, Infrastructure and Environment Executive Agency (CINEA).
• Duration: 13 April 2023 – 12 June 2025 (completed)
• Total cost: €11,332,220. · EU funding: €3,399,666.00 (30%).
• Scope: 37 Aena network airports.

e-handling is rolling out a charging network to enable ground handling operators to replace their combustion-engine vehicles with electric vehicles, in line with the European Green Deal and the Alternative Fuels Infrastructure Regulation (AFIR).

Aena’s role: As the beneficiary, Aena is installing the charging infrastructure at its Trans-European Transport Network (TEN-T) airports.

Results: 836 charging points (60 single chargers and 388 double chargers) at 37 Aena network airports.

Co-funded by the European Union. Views and opinions expressed are however those of the author(s) only and do not necessarily reflect those of the European Union or CINEA. Neither the European Union nor the granting authority can be held responsible for them.